F. SURFACE DIMENSIONING
CHAPTER F 'SURFACE DIMENSIONING' 19 ⮚ Uncheck the additive for Z Upper and place such an armature, so as to cover 8.25 cm2/m, for example Φ12/13 (8.70 cm2/m) and press the button " Update ." Now, apparently the proficiency check comes up with zero and we have met our requirement. ⮚ Also, another way to implement the Z Upper placed reinforcement would be to change the minimum reinforcement to meet the 8.26 cm2/m requirement. Recall that in this way the minimum armament, because it is uniform, will change for all four cases (X, Z, Upper, Lower) Check the " Additive " option for Z Upper, reset the "Per" and press the " Update ." Now and at Z Ano the minimum armament that was originally calculated F14/15 has been reintroduced. With the window open we select from the " Parameters " menu and set the minimum reinforcement everywhere to F12/13 which we know covers the requirement for Z Upper.