EXAMPLE 2. FORMAL STUDY METAL CONSTRUCTION

EXAMPLE 2: 'DESIGN OF A METAL STRUCTURE' 13 - as a number of 8 (IPE 100 with 90 o angle-left and right) and - as a number of 4 (IPE 100 with 0 o angle-left and right). Then you can insert the frontal poles (in this example there are no frontal poles) and the headwinds . For the horizontal wind resistors you choose cross-section CHS114.3/5.0 and place them on the first and last facade. In the places where these will be inserted you have 4 options. You choose the "upper and lower poles". Thus, the windbreaks start frompole nodes and end at nodes of the ridge, running through the intermediate tectiforms without being connected. Also, if you don't select the "intersection" the antifans will not split in the middle resulting in 2 cross members. Otherwise we would have 4 which would connect in the middle to form a single node. For the vertical upwinds on the left and right (not front and back for the example) you select cross sections CHS219.1/6.3 and positions "upper and lower posts". Finally, select the cross-sections of the pedestals (150cmx150cm rectangular cross-section pedestals) and the soil index Ks=0,50Mpa/cm.

RkJQdWJsaXNoZXIy NTIwNzc=